Critical path method for PE Civil Construction

Use a consistent forward-pass, backward-pass, and float-check sequence to identify project duration and critical activities.

Reviewed for the current ReasonSpan™ exam profile · Updated September 6, 2026

The governing sequence

The forward pass determines earliest start and earliest finish. At a merge, use the maximum incoming earliest finish. The backward pass determines latest finish and latest start. At a burst, use the minimum outgoing latest start. Total float is LS - ES or LF - EF.

Exam-ready workflow

  • Confirm the precedence relationships before calculating dates.
  • Complete the full forward pass and identify the project duration.
  • Begin the backward pass from the project completion time.
  • Calculate total float consistently and identify the controlling path.
  • When durations or logic change, recompute the network rather than modifying only one activity.

Common failure modes

A frequent error is using the minimum predecessor finish at a merge or the maximum successor start in the backward pass. Another is calling every zero-float activity critical without checking whether the activities form a continuous controlling path under the stated calendar and constraints.