Critical path method for PE Civil Construction
Use a consistent forward-pass, backward-pass, and float-check sequence to identify project duration and critical activities.
Reviewed for the current ReasonSpan™ exam profile · Updated October 11, 2026By the ReasonSpan™ editorial team · Our content standards
Worked construction network: merge logic and a delayed inspection
Original network: E, excavation, takes 4 days. Then F, foundation work, takes 6 days, while U, utility work, takes 3 days. I, a 2-day inspection and closeout, starts only after both F and U finish. All links are finish-to-start, with no lags, calendars or resource constraints; count elapsed days from Day 0.
E finishes at Day 4. F runs Day 4–10 and U Day 4–7. I waits until Day 10 and finishes at Day 12. E–F–I is the 12-day critical path. The backward pass gives U a latest finish of Day 10 and latest start of Day 7, so U has 3 days of total and free float here.
A 2-day delay to U’s start uses float and leaves the finish at Day 12. A 4-day delay moves U’s finish to Day 11, I’s start to Day 11 and the project finish to Day 13. Shortening U alone before that delay will not shorten the original 12-day schedule. Total and free float coincide in this simple network; they need not in networks with other successors or constraints.
| Activity | ES / EF | LS / LF | Total float |
|---|---|---|---|
| E | 0 / 4 | 0 / 4 | 0 days |
| F | 4 / 10 | 4 / 10 | 0 days |
| U | 4 / 7 | 7 / 10 | 3 days |
| I | 10 / 12 | 10 / 12 | 0 days |
The governing sequence
The forward pass determines earliest start and earliest finish. At a merge, use the maximum incoming earliest finish. The backward pass determines latest finish and latest start. At a burst, use the minimum outgoing latest start. Total float is LS - ES or LF - EF.
Exam-ready workflow
- Confirm the precedence relationships before calculating dates.
- Complete the full forward pass and identify the project duration.
- Begin the backward pass from the project completion time.
- Calculate total float consistently and identify the controlling path.
- When durations or logic change, recompute the network rather than modifying only one activity.
Common failure modes
A frequent error is using the minimum predecessor finish at a merge or the maximum successor start in the backward pass. Another is calling every zero-float activity critical without checking whether the activities form a continuous controlling path under the stated calendar and constraints.