PMP · formula and decision index

PMP formulas and decisions: find EVM, float, Agile flow and benefits practice

Find CPI, SPI, EAC and TCPI with their assumptions, then open complete worked examples for schedule, Agile roles, flow metrics and benefits.

Reviewed for the current ReasonSpan™ exam profile · Updated October 11, 2026
Apply this guide to your exam.No account or payment required for the sample, lesson or course preview.

Start with the decision, then choose the relationship

A correct formula needs the right status date, quantities and forecasting assumption. This index links to worked teaching, not protected mock answers. Currency-valued schedule variance is not a duration, and an observed metric is not approval to change a baseline.

Question to answerRelationship or decisionBoundary
How efficient is actual spending?CPI = EV / AC; CV = EV − ACUse comparable EV and AC at one status date.
How much budgeted work is complete versus planned?SPI = EV / PV; SV = EV − PVSPI does not alone establish critical-path delay; SV is in budget units.
What if current cost efficiency persists?EAC = BAC / CPIThis assumes the current efficiency represents remaining work.
What if remaining work occurs at the original budget rate?EAC = AC + (BAC − EV)This assumes prior variance is atypical and does not recur.
What if a new bottom-up remaining estimate is available?EAC = AC + bottom-up ETCUse the authorized, supportable remaining estimate.
What efficiency would meet the original budget?TCPI(BAC) = (BAC − EV) / (BAC − AC)A zero or negative remaining-budget denominator needs explicit interpretation.
What efficiency would meet an authorized revised estimate?TCPI(EAC) = (BAC − EV) / (EAC − AC)Use an authorized target, not whichever denominator makes the number favorable.
What is forecast budget variance?VAC = BAC − EAC; ETC = EAC − ACValidate the EAC assumption first.
Can an activity move without moving the finish?Total float = LS − ES = LF − EFRecalculate after logic, constraints or durations change.

Open the complete worked explanations

Connect calculations to a responsible action

Investigate the cause, confirm the data and remaining-work assumptions, compare authorized options and involve the appropriate owner. A CPI below one does not tell you to hide costs or automatically cancel a project. A flow forecast is not a promise that every item finishes by the same date.

The full course separates self-reported participation screening from server-graded application checks. Scheduled study targets are not earned hours; the public preview records no certificate credit.